Subscribe

Feed-in Tariff Models for Renewable Energy – biomass, cogen, mini-hydro, wind, solar and ocean thermal (OTEC)

April 29th, 2010 Posted in feed-in tariff

Feed-in Tariff Models for Renewable Energy – biomass, cogen, mini-hydro, wind, solar and ocean thermal (OTEC)

Renewable energy feed-in tariffs for biomass, biomass cogen, mini-hydro or run-of-river hydro, wind, solar PV and ocean thermal energy conversion (OTEC) have been calculated using a project finance model prepared for the National Renewable Energy Board (NREB) by Marcial Ocampo – your favorite energy technology expert.

Using standard assumptions of supplier FOB, the all-in capital cost is calculated.  The summary sheet of the model then summarizes the assumptions and results.

Marcial Ocampo

Energy & Business Development Consultant

The summary sheet of the model is shown below:

Executive Summary
WIND POWER PLANT
Investors’ Returns: NPV-FC
Equity IRR (% p.a.) 16.00%
Payback Period (years) 6.45
Uses and Sources of Funds During Construction: 000 US$ $ / kW
Uses of Funds:
Total Investment in Land (10 PhP/sqm) x (10,000 sqm/ha) 4.26 $0
Freight on Board = FOB USA = $/kW 45,000.00 $1,500
Ocean Freight = FRT = 5% x FOB 2,250.00
Insurance = INS = 1% x FOB 450.00
Cargo, Insurance & Freight = CIF = FOB + FRT + INS 47,700.00
Value Added Tax = VAT = 12% x CIF 5,724.00
Customs Duty = (CIF + VAT) x (% Duty) x (1 + % VAT) 0.00
Duty-Paid Landed Cost = DPLC = CIF + VAT + Duty 53,424.00
Local Freight Cost = LFC = 3% x CIF 1,431.00
Delivered Cost at Site = DCS = DPLC + LFC 54,855.00
Installation Cost = IC = 5% x FOB 2,250.00
Transmission line cost 69 kV (2,000,000 PhP/km) = T/L 851.06
Total EPC = DCS + IC + T/L 57,956.06
Contingency (10%) = EPC x 10% 5,795.61
Documentary Stamps (1%) = EPC x 1% = DS 579.56
Total Fixed Assets (EPC + Contingency + DS) 64,331.23 $2,144
Capitalized Expenses:
Development costs (developer, modeler) 1,286.71
Other Costs including taxes, contingencies 0.00
Carbon Emission Registration & Consultancy 30.00
Total Investment in Capitalized Expenses 1,316.71 $44
Working Capital:
months
Working capital (adjustment to meet DSCR = 1.1) 0.00
Expenses from fuel consumption 0.00 2
Maintenance of wind turbine/generator (spares) 1.13 2
Utilities (fuel, lubes, electricity, water) 2.54 3
Maintenance of the rest of the plant 244.52 3
Personnel expense 244.52 3
Land lease, rent 1.33 1
Taxes, Insurance, services, and others 32.60 1
Transport 16.30 1
Total Working Capital 542.95 $18
Interest During Construction (IDC):
Dev’t fees (developer, loan arranger) 661.95
Front end fees (modeler, loan arranger) 661.95
Commitment fees (bank) 330.98
Interest During Construction (bank) – 12 months 5,295.61
Total Legal & Financing Fees and IDC 6,950.49 $232
Total Uses of Fund, ’000 US$ 73,145.64 $2,438
Sources of Fund:
% to be financed by capital 21,943.69 30.00%
% to be financed by non refundable subsidy 0.00 0.00%
% to be financed by debt 51,201.95 70.00%
Total Sources of Fund, ’000 US$ 73,145.64 100.00%
Weighted Average Cost of Capital (WACC): Returns
Equity 16.00% 30.00%
Subsidy 0.00% 0.00%
Debt 10.00% 70.00%
WACC 11.80%
Rated Capacity:
Unit Capacity of WTG (MW/unit) 2.000
No. of TWG (unit) 15
Total Gross Installed Capacity (MW) 30.000
National Renewable Energy Board
Feed-in Tariff (FiT) Calculation Procedure
Generation and Sales:
Capacity Factor (% of rated) 25.00%
Days per year 365
Hours per day 24
Gross Generation (MWh/year) 65,700
Power Plant Own Use (%) 5.000%
3,285
Net Generation (MWh/year) 62,415
Transmission Line Loss assumed (%) 3.000%
1,872
Net Sales (MWh/year) 60,543
Transmission Line:
Line Voltage 69 kV
Power 30,000 kW
Length 20.000 km
Power Factor 0.850 lag
No. of Circuit 3
Transmission Line Loss calculated (%) 1.365%
Cost per km: 2,000,000 PhP
42,553 $
Capital and O&M Cost Assumptions:
First Year Tariff (PhP/kWh) 12.3868
Cost per kW FOB USA ($/kW) 1,500
Variable O&M ($/kWh): 0.000267
Maintenance of wind turbine/generator (spares) 6.77 000 US$
Utilities (fuel, lubes, electricity, water) 10.16 000 US$
Fixed O&M ($/kW/year): 0.0853
Maintenance of the rest of the plant 978.09 000 US$
Personnel expense 978.09 000 US$
Land lease, rent 15.96 000 US$
Taxes, Insurance, services, and others 391.24 000 US$
Transport 195.62 000 US$
Debt Service Reserve Fund:
Months of debt service 6
DSRF Income -interest on Foreign Currency Deposit 4.0%
Withholding Tax on Foreign Currency Deposit 7.5%
DSRF Expense 0.30%
Taxes and Regulatory Costs:
Special Privilege Tax – 2% 1.00%
Special Realty Tax – 2.5% 1.50%
DOE 1-94 : 0.01 PhP/kWh sales 0.01
Corporate income tax rate (% of taxable income) 10%
Income tax holiday (ITH), years 7
Profit Sharing, % of IAT 0.00%
Social Benefit Fund – Host Community, PhP/month 0
Working Capital Needs: months
Cash needed for operations (+) 3.00
Customers / Receivables (+) 1.00
Stocks / Inventory (+) 2.00
Suppliers / Payables (-) 1.00
Exchange Rate and Escalation: 0 No Escalation
Exchage Rate, PhP / US$ 47.00 0.00% depreciation
RP CPI (Local) 5.00% local escalation
US CPI (Foreign) 2.50% foreign escalation
Variable O&M: weight 0.00% variable escalation
% Local (30%) 50.00% 5.00%
% Foreign (70%) 50.00% 2.50%
Fixed O&M: weight 0.00% fixed escalation
% Local (70%) 50.00% 5.00%
% Foreign (30%) 50.00% 2.50%
Loan:
Interest rate of debt, % p.a. 10.00%
Loan term, years 12
Grace period (construction period), months 12.00

6 Responses to “Feed-in Tariff Models for Renewable Energy – biomass, cogen, mini-hydro, wind, solar and ocean thermal (OTEC)”

  1. Deon Cannuli Says:

    I simply found your site, I actually saved it and i ‘m looking through the actual posts. I witout a doubt like it. Intriguing issue in any event . you look on this. I come from the standpoint which observe commentary as akin of listening.



  2. Solar Power Renewable Alternative Energy Says:

    Hi, another helpful article for those searching for information on the subject, hopefully I will be able to put it to good use.



  3. wind power Says:

    wind power…

    [...]Feed-in Tariff Models for Renewable Energy – biomass, cogen, mini-hydro, wind, solar and ocean thermal | Energy Technology Expert[...]…



  4. M.tech ProjectsARM 9 projectsEmbedded ProjectsVLSI projectsMini ProjectsElectronics TutorialsprojectsPIC microcontrollermini 2440 Says:

    M.tech ProjectsARM 9 projectsEmbedded ProjectsVLSI projectsMini ProjectsElectronics TutorialsprojectsPIC microcontrollermini 2440…

    [...]Feed-in Tariff Models for Renewable Energy – biomass, cogen, mini-hydro, wind, solar and ocean thermal | Energy Technology Expert[...]…



  5. รายได้เสริมทางเน็ต Says:

    รายได้เสริมทางเน็ต…

    [...]Feed-in Tariff Models for Renewable Energy – biomass, cogen, mini-hydro, wind, solar and ocean thermal | Energy Technology Expert[...]…



  6. greenenergyclub Says:

    greenenergyclub…

    [...]Feed-in Tariff Models for Renewable Energy – biomass, cogen, mini-hydro, wind, solar and ocean thermal | Energy Technology Expert[...]…



Leave a Reply

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>