Subscribe

Gas Turbine and CCGT LevelizedTariff, Levelized Cost and Financial Model

November 26th, 2009 Posted in financial models

Gas Turbine and CCGT LevelizedTariff, Levelized Cost and Financial Model

The following is a snippet of my state-of-the-art project finance model for calculating levelized tariff, levelized cost of energy, and financial model (generation, fuel requirement, income statement, cash flow statement, balance sheet and financial ratios).  To secure a copy of the spreadsheet, click the ENERGY DATA page for arrangements.

PROJECT FINANCE MODEL : Simple Cycle Gas Turbine Name Simple Cycle GT
(C) Copyright 2009 by Marcial T. Ocampo (November 2009)
INSTRUCTIONS mars_ocampo@yahoo.com
(This example is in PhP Thousand, except for the unit prices which are in PhP/kWh) energydataexpert@gmail.com
Year 0 reflects the starting assumptions, which will be applicable starting in year 1.

Select NPV to use (1)

6.2373

NPV

IRR

Payback

Blue cells must be filled out by the user.

NPV-ROI

0

(990,417)

4.59%

31.49

Escalate fuel, lubes, tariff and O&M costs? (1=yes, 0=no)

0

NPV-ROE

1

0

15.00%

9.77

CALCULATION OF GROSS OPERATING MARGIN

NPV-FC

0

(50,350)

13.66%

10.04

NPV-FC discounted

0

(132,495)

10.96%

10.54

Year

used

0.00

2009

2010

2011

Days Per Year

365

365

365

Hours Per Day

24

24

24

24

Plant Operation

365

Year

0

1

2

Overhaul Cycle

0

1

2

Capacity Degradation
Normal, % p.a.

1.50%

1.0000

1.0150

1.0302

Overhaul, % p.a.

-5.25%

1.50%

1.50%

Overhaul Cycle, yr

5

Recovery, %

70.00%

Select Manufacturer/Engine Model:

MW

Heat Rate, kJ / kWh

Efficiency, %

Cost, $/kW

Variable O&M

Fixed O&M

Simple Gas Turbine Aero Derivative GT

35.000

9,142

39.38%

325

0.005

0.040

Recuperated GT

3.200

8,889

40.50%

400

0.005

0.040

CHAT 11 MW GT

11.000

8,090

44.50%

800

0.005

0.040

CHAT 300 MW GT

300.000

6,581

54.70%

375

0.005

0.040

Heavy Frame GT

200.000

10,286

35.00%

560

0.005

0.040

SGT6-5000F (Siemens Westinghouse) – CCGT

264.061

6611

54.45%

831.46

0.002

0.150

Plant Rated Capacity, MW

35.000

9,142

39.38%

325.00

35.000

35.000

Dependable Capacity, MW

34.483

33.973

Plant Availability
Calendar Days

365.24

365

365

Total Period Hours

24

8760

8760

Planned Overhaul, days (4 wks)

28

Regular Maintenance, days (2 wks)

14

14

14

Economic S/D, % of CD

0.20%

0.73

0.73

Deactivated S/D – External, % of CD

0.50%

1.83

1.83

Total Unforced Outage, days

16.56

16.56

Forced Outage – Internal, % of CD

6.00%

21.90

21.90

Total Outage, days

41.27

38.46

38.46

Total Operating Hours

7,775

7,837

7,837

Plant Statistics
Outage Rate = FO*24/ (FO*24+TOH)

6.34%

6.29%

6.29%

Availability = TOH/PH

88.70%

89.46%

89.46%

Equivalent Availability

88.76%

87.45%

Reliability = 1-OR

93.66%

93.71%

93.71%

Generation and Capacity Factor
Load Factor, % of DC

93.00%

93.00%

93.00%

Potential Generation = DC*LF*TOH MWh

251,327

247,613

Rated Generation =  RC*PH MWh

306,600

306,600

Capacity Factor = PG / RG

76.57%

81.97%

80.76%

Plant Heat Rate

Typical

Actual GT Engine

Gas Turbine Output (1 / 3)

40.00%

Steam Turbine Input (2 / 3)

Boiler Efficiency at 1% cont. BD

Steam Turbine Efficiency

Mechanical Drive / Clutch Efficiency

99.00%

Generator Efficiency

96.00%

Overall Efficiency=(GT+ST*BE*STE)*ME*GE

38.02%

39.38%

Plant Heat Rate at 100% eff.

3412.12822

Plant Heat Rate, Btu / kWh = 3412/ OE

8,976

8,665

8,665

8,665

Heat Rate (Efficiency) Degradation

Normal, % p.a.

1.50%

1.0000

1.0150

1.0302

Overhaul, % p.a.

-5.25%

1.50%

1.50%

Overhaul Cycle, yr

5

Recovery, %

70.00%

Actual Plant Heat Rate, Btu/kWh

8,795

8,927

Actual Overall Efficiency, % of fuel GHV

38.80%

38.22%

Net Electricity Sales, MWh
Potential Generation

251,327

247,613

Step-up Transformer Loss (Switchyard), MWh

1.00%

1.00%

1.00%

Generation at Plant Fence

248,814

245,137

Transmission Line Losses, MWh

2.00%

2.00%

2.00%

Net Electricity Sales to Customer

243,838

240,234

Other Losses (non-technical, pilferage), MWh

0.00%

0.00%

0.00%

Electricity sales to the network (MWh)

243,838

240,234

Annual increase of the volume, % p.a.

0.0%

-1.5%

Fuel Consumption
Gross Generation (Potential Generation), MWh

251,327

247,613

Plant Heat Rate, Btu/kWh

8,795

8,927

Total Energy Input to be supplied by fuel, Million Btu

2,210,476

2,210,476

Energy Supplied by each fuel, Million Btu:

GHV, Btu/lb

NHV, Btu/lb

GHV / NHV

Natural Gas (Malampaya Gas) – main fuel

22,129

20,249

1.093

2,099,952

2,099,952

Diesel Oil – backup fuel (gas pipeline downtime)

19,650

18,453

1.065

110,524

110,524

Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel

18,400

17,449

1.055

88,419

88,419

Bunker Fuel Oil (BFO – 3% S) – boiler fuel

19,670

18,565

1.060

22,105

22,105

Fuel Consumption, Million Liters:

kg / Liter

GHV, Btu/Liter

Natural Gas (Malampaya Gas) – main fuel

1.05506

kJ / Btu

GJ (Million kJ)

2,215,575

2,215,575

Diesel Oil – backup fuel

0.8448

36,597

Million Liters

3.020

3.020

Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel

0.9659

39,181

Million Liters

2.257

2.257

Bunker Fuel Oil (BFO – 3% S) – boiler fuel

0.8916

38,664

Million Liters

0.572

0.572

Total Million Liters

5.848

5.848

Specific Fuel Consumption, Liters / kWh

0.023

0.024

Fuel Cost, Million PhP:

PhP / Liter 2009

Escalation

$ / Million Btu

Natural Gas (Malampaya Gas) – main fuel, 8.628 $/GJ

418.11

0.00%

PhP / GJ

9.10

926.361

926.361

Diesel Oil – backup fuel

30.00

0.00%

PhP / Liter

16.92

90.601

90.601

Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel

23.24

0.00%

PhP / Liter

12.24

52.437

52.437

Bunker Fuel Oil (BFO – 3% S) – boiler fuel

22.51

0.00%

PhP / Liter

12.01

12.867

12.867

Total Fuel Cost, Million PhP

155.905

155.905

Average fuel cost, PhP/Liter

26.66

26.658

26.658

Average fuel cost escalation, % p.a.

0.00%

0.0%

0.0%

Lube Oil Consumption
Normal, % p.a.

1.50%

1.0000

1.0150

1.0302

Overhaul, % p.a.

-5.25%

1.50%

1.50%

Overhaul Cycle, yr

5

Recovery, %

70.00%

Ideal Lube Oil Consumption, g/kWh

0.254

0.254

0.254

Actual Lube Oil Consumption, g/kWh

0.257

0.261

Lube Oil Consumption, Million Liters

0.8500

kg/Liter

0.076

0.076

Lube Oil Cost, Million PhP

149.87

0.00%

11.402

11.402

Average lube oil cost, PhP/Liter

149.871

149.871

Average lube oil escalation, % p.a.

0.00%

0.0%

0.0%

A) Operating income: ’000 PhP

365

Year

0

1

2

Electric tariff for sales to the network (PhP/kWh)

6.2373

6.2373

6.2373

Annual increase of the tariff, % p.a.

0.00%

0.00%

0.00%

Income from sales to DU, ’000 PhP

1,064,614

1,048,881

Electricity sales to DU, MWh

70.00%

of sales

170,686

168,164

Electricity tariff to DU, PhP/kWh

100.00%

6.2373

discount tariff (direct customers)

6.2373

6.2373

Income from sales to NPC, ’000 PhP

304,176

299,680

Electricity sales to NPC, MWh

20.00%

of sales

48,768

48,047

Electricity tariff to NPC, PhP/kWh

100.00%

6.2373

reference tariff (average grid)

6.2373

6.2373

Income from sales to WESM, ’000 PhP

152,088

149,840

Electricity sales to WESM, MWh

10.00%

of sales

24,384

24,023

Electricity tariff to WESM, PhP/kWh

100.00%

6.2373

WESM tariff (wholesale spot market)

6.2373

6.2373

TOTAL OPERATING INCOME

1,520,878

1,498,402

Annual increase in Operating Income

0.0%

-1.5%

Total electricity sales to DU, NPC, and WESM, MWh

243,838

240,234

Average Electricity Tariff, PhP/kWh

6.2373

6.2373

Annual increase in Electricity Tariff

0.00%

0.0%

0.0%

B) Expenses: ’000 PhP

Year

0

1

2

Consumption of natural gas fuel, ’000 GJ

2,216

2,216

Annual increase of the volume

0.0%

0.0%

Price of natural gas fuel (PhP/GJ)

418.113

418.113

Annual increase of the price

0.0%

0.0%

Total Natural Gas Fuel Cost

926,361

926,361

Consumption volume of fuel, ’000 liters

5,848

5,848

Annual increase of the volume

0.0%

0.0%

Price of liquid fuel (PhP/Liter)

26.658

26.658

Annual increase of the price

0.0%

0.0%

Total Liquid Fuel Costs

Escalation

months

working capital

155,905

155,905

Total Fuel Costs

2

180,378 1,082,265

1,082,265

1,082,265

Annual increase of fuel costs

0.0%

0.0%

Expenses from lube purchase

2

1,900 11,402

11,402

11,402

Purchase of chemical materials

0.00%

2

3,802 22,813

22,813

22,476

Utilities (electricity, water)

0.00%

2

3,802 22,813

22,813

22,476

DOE 1-04 (0.01 PhP/kWh sold)

2

406 2,438

2,438

2,402

Total Variable O&M

9,911

59,467

58,756

Annual increase of variable O&M

-0.46%

0.0%

-1.2%

Variable O&M, $/kWh

48.46

0.00494

0.00488

0.00490

Maintenance of the installation

0.00%

2

5,070 30,418

30,418

29,968

Personnel expense

0.00%

2

3,042 18,251

18,251

17,981

Land lease, rent

0.00%

2

2,535 15,209

15,209

14,984

Other services

0.00%

2

1,267 7,604

7,604

7,492

Total Fixed O&M

11,914

71,481

70,425

Annual increase of fixed O&M

-0.53%

0.0%

-1.5%

Fixed O&M, $/kW/year

48.46

0.0394

0.04214

0.04152

Taxes, Insurances, Benefits & Regulatory Costs

0.00%

0

25,842

29,377

DSRF Expense

0.30%

0

318

300

total working capital

TOTAL OPERATING EXPENSE

202,202

1,239,373

1,241,123

Annual increase

-0.21%

0.1%

GROSS OPERATING MARGIN

281,505

257,278

Annual increase

-1.32%

-8.6%

PROFIT AND LOSS STATEMENTS
In ’000 PhP

Year

0

1

2

Operating income

1,520,878

1,498,402

Operating expense

1,239,373

1,241,123

Operating gross margin

281,505

257,278

- Depreciation & amortization

50,576

50,576

- Interest

112,908

101,023

NET PROFIT BEFORE TAX

118,021

105,680

(Tax rate) and Income Tax Holiday (ITH) years

30%

0

30%

30%

- Income tax

35,406

31,704

NET PROFIT AFTER TAX

82,615

73,976

Percentage of increase

-10.5%

NET CASH FLOW

Year

0

1

2

Net profit after tax

82,615

73,976

Addback:
Depreciation & Amortization

50,576

50,576

Working Capital
Salvage Value
Add:
DSRF Income

4.00%

DSRF Income

4,239

4,001

Less:
Principal Repayment

99,042

99,042

Profit Sharing

0.00%

of income after tax

0

0

Social Benefit Fund – Host Community

0

per month

0

0

NET CASH FLOW

38,388

29,511

Percentage of increase

-23.1%

Total Initial investment

1,414,881

Project Cash Flow

4.59%

12.90%

WACC

-1,414,881

38,388

29,511

IRR

NPV

-990,417

-1,414,881

33,381

22,315

check

-894,807

-1,414,881

34,002

23,153

cumulative

0

-1,414,881

-1,376,493

-1,346,981

project payback

31.49

Invested capital

30.00%

424,464

Equity Cash Flow

15.00%

15.00%

Equity IRR

-424,464

38,388

29,511

IRR

NPV

0

-424,464

33,381

22,315

check

0

-424,464

33,381

22,315

cumulative

0

-424,464

-386,076

-356,565

equity payback

9.77

CALCULATION OF CASH FLOW FOR DEBT SERVICE

Year

0

1

2

Operating gross margin

281,505

257,278

- Income tax

35,406

31,704

- Increase in working capital needs (WCN)

234,799

-2,137

- Profit Sharing

0

0

+ DSRF Income

4,239

4,001

- Social Benefit Fund

0

0

Cash flow available for debt service (CFD)

15,538

231,713

CALCULATION OF DEBT SERVICE COVERAGE RATIO (DSCR)

Year

0

1

2

Cash flow available for debt service (CFD)

15,538

231,713

Annual debt service (DS)

211,949

200,064

DEBT SERVICE COVERAGE RATIO (DSCR)

0.07

1.16

CALCULATION OF DIVIDENDS PAYABLE

Year

0

1

2

Cash flow available for debt service (CFD)

15,538

231,713

Annual debt service (DS)

211,949

200,064

CF available for dividends (CFDiv = CFD-DS)

0

31,649

Accumulated CFDiv

0

0

31,649

Current year profit after tax

82,615

73,976

Accumulated profit: limit for dividend payable

0

82,615

156,591

0

31,649

Accumulated dividend payable

0

0

31,649

Annual dividend payable

0

31,649

CALCULATION OF NPV, IRR AND PAY-BACK ACCORDING TO INVESTED CAPITAL AND DIVIDENDS PAYABLE

Year

0

1

2

Invested capital

424,464

Annual dividend payable

0

0

31,649

Discount rate to be applied for NPV calculation

15.00%

15%

15%

Discount factor for this rate

1.0000

1.0000

1.1500

1.3225

Discounted dividends

0

0

23,931

Present value of dividends

374,114

NPV of the investment

-50,350

Year

0

1

2

Investment schedule

13.66%

15.00%

Equity IRR

-424,464

0

31,649

IRR of Invested Capital

IRR

NPV

-50,350

-424,464

0

23,931

check

-50,350

-424,464

0

23,931

cumulative

0

-424,464

-424,464

-392,816

Pay-back term of invested capital, years

equity payback

10.04

BALANCE SHEET ACCOUNTS
Calculation of Working Capital Needs (WCN):

Cash needed for operations (+)

3.00

months of expenses

17,870

17,606

Customers / Receivables (+)

1.00

months of revenue

126,740

124,867

Stocks / Inventory (+)

2.00

months of fuel & chemicals

184,180

184,124

Suppliers / Payables (-)

1.00

months of payables

93,991

93,935

WCN

15.80%

% of operating income

234,799

232,662

CALCULATION OF DEPRECIATION
In ’000 PhP

Year

0

1

2

Initial investment in land (PhP/ha), 1 ha = 10,000 m2

1,000,000

10

ha 10,000
Freight on Board = FOB USA = $/kW

15,750

35.000

MW 551,233
Ocean Freight = FRT = 5% x FOB

5%

27,562
Insurance = INS = 1% x FOB

1%

5,512
Cargo, Insurance & Freight = CIF = FOB + FRT + INS 584,306
Value Added Tax = VAT = 12% x CIF

12%

70,117
Customs Duty = (CIF + VAT) x (% Duty) x (1 + % VAT)

3%

21,989
Duty-Paid Landed Cost = DPLC = CIF + VAT + Duty 676,412
Local Freight Cost = LFC = 3% x CIF

3%

17,529
Delivered Cost at Site = DCS = DPLC + LFC 693,941
Installation Cost = IC = 5% x FOB

5%

27,562
Total EPC = DCS + IC 721,503
Contingency (10%) = EPC x 10%

10%

72,150
Documentary Stamps (1%) = EPC x 1% = DS

1%

7,215
Total Fixed Assets (EPC + Contingency + DS) 800,868
Depreciation term (years)

salvage

10.00%

28,831

25

810,868

Development costs (modeler)

1.00%

8,109
Other Costs including taxes, contingencies

12.00%

97,304
Initial investment in capitalized expenses 307,615

105,413

Amortization term (years)

salvage

10.00%

11,074

25

Working Capital:
Working capital (initial stocks – fuel) – 2 months 180,378
Working capital (initial stocks – lubes) – 2 months 1,900
Working capital (initial stocks – chemical materials) – 2 months 3,802
Working capital (mobilization – utilities) – 2 months 3,802
Working capital (mobilization – DOE 1-94) – 2 months 406
Working capital (mobilization – maintenance) – 2 months 5,070
Working capital (mobilization – personnel expense) – 2 months 3,042
Working capital (pre-paid expense – advance rent) – 2 months 2,535
Working capital (pre-paid expense – other services) – 2 months 202,202 1,267

1,118,483

Interest During Construction:
Dev’t fees (loan arranger)

1.00%

11,185
Front end fees (loan arranger)

1.00%

11,185
Commitment fees (bank)

0.50%

5,592
Interest During Construction (bank) – 24 months

2.00

12.00%

268,436

296,398

Amortization term (years)

salvage

10.00%

10,670

25

Total Investment (land, fixed, capitalized expenses, working capital) 1,414,881
Depreciation of fixed assets

28,831

28,831

Amortization of capitalized expenses (development costs, working capital)

11,074

11,074

Amortization of capitalized expenses (IDC)

10,670

10,670

TOTAL DEPRECIATION & AMORTIZATION EXPENSE

50,576

50,576

Evolution of fixed assets and capitalized expenses

Year

0

1

2

Land (non-depreciable)

10,000

10,000

10,000

Gross fixed assets  (PPE, Building, Civil Works)

800,868

800,868

800,868

Accumulated depreciation

0

28,831

57,662

Net fixed assets

800,868

772,037

743,205

Gross capitalized expenses (Development Costs, Working Capital)

307,615

307,615

307,615

Accumulated amortization

0

11,074

22,148

Net capitalized expenses

307,615

296,541

285,467

Gross capitalized interest during construction (IDC)

296,398

296,398

296,398

Accumulated amortization

0

10,670

21,341

Net capitalized interest during construction (IDC)

296,398

285,728

275,057

Total Depreciable Assets (fixed assets, capitalized expenses, IDC)

1,404,881

1,354,305

1,303,730

Taxes, Insurances, Benefits & Regulatory Costs

Year

0

1

2

Real Property Tax – Land

1.60%

of land

160

160

Real Property Tax – PPE

1.60%

of fixed assets

12,353

11,891

Real Property Tax – Buildings

0.80%

of building
Land Lease & ROW

0.00

PhP/MT coal
Property Insurance – PPE

0.78%

of fixed assets

6,247

6,247

Property Insurance – Building

0.78%

of building
Business Interruption Insurance

0.56%

of previous year’s revenue

4,485

8,517

Special Education Fund – benefits to host community

1.00%

of land

100

100

SEC Registration & Fees

3,919

3.92

3.92

BIR Registration & Fees

530

0.53

0.53

DENR Permits & Fees

99

0.10

0.10

Discharge Fee (BOD, TSS) – DENR

0

0.00

0.00

EMB Permits & Fees

396

0.40

0.40

NWRB Permits & Fees

17,417

17.42

17.42

PNRI Permits & Fees

5,900

5.90

5.90

ERC Registration & Fess

1,500

1.50

1.50

DOLE Permits & Fees

212

0.21

0.21

DTI Permits & Fees

0

0.00

0.00

LGU Registration & Fees

2,009

2.01

2.01

NTC Registration & Fees

28

0.03

0.03

BOC Registration & Fees

5,000

5.00

5.00

PPA Registration & Fees

1,000

1.00

1.00

ATO Registration & Fees

13,050

13.05

13.05

PDEA Registration & Fees

3,000

3.00

3.00

BOI Registration & Fees

4,500

4.50

4.50

DOE Permits & Fees

800

0.80

0.80

Local Business Taxes (1/2 of 1% of GR)

0.00%

of gross revenue

0

0

National Franchise Taxes (1/2 of 1% of GR)

0.00%

of gross revenue

0

0

DOE 1-94 (PhP 0.01 per kWh sold)

0.01

per kWh sold

2,438

2,402

Total Taxes, Insurances & Regulatory Costs

25,842

29,377

DEBT SERVICE CALCULATION
In ’000 PhP

Year

0

1

2

Total Initial investment

1,414,881

% to be financed by capital

Equity IRR

15.00%

30.00%

% to be financed by non refundable subsidy

Subsidy

0.00%

0.00%

% to be financed by debt

Debt Interest

12.00%

70.00%

Initial amount of capital

WACC

12.90%

424,464

Amount of subsidy

0

Initial amount of debt

990,417

Repayment term (years) 99,042

10

Constant Repayment Method:
Annual repayment

99,042

99,042

Amount of debt at year end

990,417

891,375

792,333

Average amount of debt

940,896

841,854

Reference interest rate (Libor or other)

10.00%

10.00%

10.00%

Spread

2.00%

2.00%

2.00%

Interest rate of debt

1

12.00%

12.00%

12.00%

Interest based on average amount of debt

112,908

101,023

Declining Balance Method:
Beginning Balance

990,417

933,979

Interest based on beginning balance

0

17.70%

12.00%

118,850

112,077

Principal repayment 175,288

10

56,438

63,211

Remaining balance

990,417

933,979

870,768

Year

0

1

2

Beginning Balance

990,417

891,375

Annual amount of interest

112,908

101,023

Annual amount of principal

99,042

99,042

Annual debt service (principal + interest)

211,949

200,064

Ending Balance

990,417

891,375

792,333

Debt Service Reserve Fund

6

months of debt service

105,975

100,032

DSRF Income -interest on Foreign Currency Deposit

4.00%

DSRF Income

4,239

4,001

Withholding Tax on Foreign Currency Deposit

7.50%

WHTax
DSRF Expense – withholding tax

0.30%

DSRF Expense

318

300

BALANCE SHEET
BALANCE SHEET BEFORE DIVIDEND PAYMENT
In ’000 PhP

Year

0

1

2

Cash needed for operations

0

17,870

17,606

Additional cash (if negative, it would represent additional debt)

0

-200,650

-173,003

Receivables / Customers

0

126,740

124,867

Stocks / Inventory

0

184,180

184,124

Land

10,000

10,000

10,000

Fixed assets (net)

800,868

772,037

743,205

Capitalized expenses (net)

307,615

296,541

285,467

Capitalized IDC (net)

296,398

285,728

275,057

Total assets

1,414,881

1,492,445

1,467,324

Suppliers / Payables

0

93,991

93,935

Debt

990,417

891,375

792,333

Shareholder’s Advances
Current year profit after tax

0

82,615

73,976

Accumulated reserves

0

0

82,615

Subsidy

0

0

0

Capital

424,464

424,464

424,464

Total liabilities and net worth

1,414,881

1,492,445

1,467,324

variance

- - -
BALANCE SHEET AFTER DIVIDEND PAYMENT

Year

0

1

2

Cash needed for operations

0

17,870

17,606

Additional cash (if negative, it would represent additional debt)

0

-200,650

-204,651

Receivables / Customers

0

126,740

124,867

Stocks / Inventory

0

184,180

184,124

Land

10,000

10,000

10,000

Fixed assets (net)

800,868

772,037

743,205

Capitalized expenses (net)

307,615

296,541

285,467

Capitalized IDC (net)

296,398

285,728

275,057

Total assets

1,414,881

1,492,445

1,435,675

Suppliers / Payables

0

93,991

93,935

Debt

990,417

891,375

792,333

Shareholder’s Advances
Current year profit after tax
Reserves

0

82,615

124,943

Subsidy

0

0

0

Capital

424,464

424,464

424,464

Total liabilities and net worth

1,414,881

1,492,445

1,435,675

variance

- - -
Calculation of Dividends Payable
Gross Margin

281,505

257,278

Income Tax (-)

35,406

31,704

Increase in Working Capital (-)

234,799

-2,137

Profit Sharing (-)

0

0

DSRF Income (+)

4,239

4,001

Social Benefit Fund (-)

0

0

Cash flow available for debt service (CFD)

15,538

231,713

Annual debt service (DS) = Interest + Principal

211,949

200,064

CF available for dividends (CFDiv = CFD-DS)

0

31,649

Accumulated CFDiv

0

0

31,649

Current year profit = Income After Tax

82,615

73,976

Accumulated profit: limit for dividend payable

0

82,615

156,591

Accumulated dividend payable

0

0

31,649

Annual dividend payable

planned

actual

-424,464

0

31,649

Investor 1

60.00%

56.04%

-254,679

0

18,989

Investor 2

20.00%

41.60%

-84,893

0

6,330

Investor 3

20.00%

2.36%

-84,893

0

6,330

CASH FLOW STATEMENT

Year

0

1

2

OPERATIONS
Net Income (after tax)

0

82,615

73,976

Add:  Depreciation & Amortization

0

50,576

50,576

(Increase) / Decrease in Receivables

0

-126,740

1,873

(Increase) / Decrease in Inventories

0

-184,180

56

Increase / (Decrease) in Accounts Payable

0

93,991

-56

Net Cash flow from Operations

0

-83,738

126,425

INVESTMENTS
Additions to PP&E

800,868

-800,868

0

0

Additions to Capitalized Expenses

307,615

-307,615

0

0

Additions to Capitalized IDC

296,398

-296,398

0

0

Additions to Land

10,000

-10,000

0

0

Net Cash flow Used for Investments

1,414,881

-1,414,881

0

0

Cash flow before Financing

-1,414,881

-83,738

126,425

FINANCING
Increase (Decrease) in Shareholder Advances

0

0

0

Increase (Decrease) in Long-term Debt

990,417

990,417

-99,042

-99,042

Increase (Decrease) in Subsidy

0

0

0

0

Increase (Decrease) in Capital Stock

424,464

424,464

0

0

Net Cash flow from Financing

1,414,881

1,414,881

-99,042

-99,042

NET CASH FLOW

0

-182,780

27,383

Add: Beginning Cash Balance

0

-182,780

ENDING CASH BALANCE

0.00

-182,780

-155,396

Levelized Price and Generation Cost of Electricity

Year

0

1

2

Discounting Rate, % p.a.

15.00%

48.46

NPV

Electricity sales MWh

$/kWh

PhP/kWh

1,514,166

243,838

240,234

TOTAL OPERATING INCOME (levelized price) 000 PhP

0.1287

6.2373

9,444,248

1,520,878

1,498,402

Total Fuel Costs 000 PhP

0.0948

4.5940

6,956,020

1,082,265

1,082,265

Expenses from lube purchase 000 PhP

0.0010

0.0484

73,284

11,402

11,402

Purchase of chemical materials 000 PhP

0.0019

0.0936

141,664

22,813

22,476

Utilities (electricity, water) 000 PhP

0.0019

0.0936

141,664

22,813

22,476

DOE 1-04 (0.01 PhP/kWh sold) 000 PhP

0.0002

0.0100

15,142

2,438

2,402

Maintenance of the installation 000 PhP

0.0026

0.1247

188,885

30,418

29,968

Personnel expense 000 PhP

0.0015

0.0748

113,331

18,251

17,981

Land lease, rent 000 PhP

0.0013

0.0624

94,442

15,209

14,984

Other services 000 PhP

0.0006

0.0312

47,221

7,604

7,492

Taxes, Insurances, Benefits & Regulatory Costs 000 PhP

0.0023

0.1120

169,583

25,842

29,377

DSRF Expense 000 PhP

0.0000

0.0009

1,293

318

300

- Depreciation & amortization 000 PhP

0.0045

0.2159

326,929

50,576

50,576

- Interest 000 PhP

0.0050

0.2410

364,856

112,908

101,023

- Income tax 000 PhP

0.0033

0.1605

242,980

35,406

31,704

Total Generation Cost

0.1210

5.8628

8,877,294

1,438,263

1,424,426

Net Profit

0.0077

0.3744

566,954

82,614.99

73,976.13

4 Responses to “Gas Turbine and CCGT LevelizedTariff, Levelized Cost and Financial Model”

  1. Gas Turbine and CCGT Levelized Tariff, Levelized Cost and Financial Model | Renewables Biz Says:


  2. Portland personal injury attorney Says:

    certainly, what a great web page and informative posts, im going to add backlink – bookmark this url? Regards, Reader.



  3. Planner in the desert Says:

    Question rather than a comment. I there a rule of thumb calculation to work out how much natural gas / LNG is required to provide 1 MVA of electricity from a CCGT power station?



  4. admin Says:

    Hi Donald, rather than a rule of thumb, I will provide you some inputs. You need to know the power factor so you may know the MW from the MVA. Then you need to know the overall fuel to electricity efficiency of a CCGT (around 54-56%), the natural gas/LNG heating value (kJ/kg) so you will be able to estimate the kg/s of fuel given the MW of electricity.



Leave a Reply

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>