Subscribe

Project Finance Models for Power Plants with Carbon Credits under CDM (download file)

January 4th, 2010 Posted in financial models

Project Finance Models for Power Plants with Carbon Credits under CDM (download file)

Due to worldwide interest in carbon emission reduction credits thru the clean development mechanishm (CDM) of the Kyoto Protocol to encourage renewable and energy efficiency improvement in power generation to reduce carbon emissions and mitigate global warming, I am issuing another model update for January 2009.  I also made some changes to working capital and all-in project cost estimation and loan amortization calculations.
Also due to numerous inquiries and tremendous interest, the deadline has been extend up to 31 January 2010.  Order now to get 70% discount on any project finance model of your choice.  This 2010 version now includes carbon emission reduction credits under the Clean Development Mechanism (CDM) of the Kyoto Protocol. It provides for one time cost for consultancy services and registration to the CDM Executive Board and annual carbon emission reduction credits net of annual fees for monitoring by local consultants and Executive Board.


This advanced model allows you to perform the following:

1) Determine the impact of electricity tariff (selling price) on NPV, IRR and payback given the capital cost, fuel cost and O&M cost.

2) Determine the maximum main fuel price (natural gas, gas oil) to meet IRR given electricity tariff, capital cost and O&M cost.

3) Determine the maximum capital cost (all-in) to meet IRR given electricity tariff, fuel price and O&M cost.

4) Perform sensitivity analysis (+/- 10% change) on variables such as electricity tariff, rated capacity, plant heat rate (efficiency), fuel cost, capital cost and O&M costs on IRR.

5) The IRR may be defined as DCF-ROI (project cost vs cash flow), DCF-ROE (equity portion of project cost vs cash flow), DCF-FC (equity portion vs free cashflow), and discounted DCF-FC (native currency is depreciating vs foreign currency).  The model provides for analysis with escalation (nominal IRR) and without escalation (real IRR).

6) When applied to large scale power plants, it could optimize the type of CCGT engine/manufacturer, plant location and cooling system (once thru sea water, once thru lake water, river cooling tower, deep well cooling tower, radiator cooling) and transmission line system (type of conductor).  The optimal configuration is determined by the combination that provides the cheapest electricity tariff, cheapest fuel or highest IRR.

The model includes capacity degradation, plant heat rate degradation and overhaul and maintenance cycle to determine dependable capacity, actual plant efficiency and actual plant operating hours (to determine availability and capacity factor).

The user may specify the type of system of units and currency (e.g. Peso, US$, MW, MWh, MMBtu or GJ, liters or gallons, kg or lb).

Be one of the many satisfied users of the new top-down style project finance models (minimal tabs) that allow you full control on your financial models and do all your sensitivities (tariff, demand, capex, fuel, opex, etc.).  If you believe you deserve this model, email me your particular concerns, and hopefully, allow me to address your needs.

Hit the road running with my project finance models.  Using a top-to-bottom approach, update the data as you go down the model and understanding it fully at the same time.  The user has full control – can add rows and columns as necessary.  Once you have set-up your financial model, do your sensitivity runs, then write your final feasibility study report, including the executive summary and appendices.  I can provide you template financial models and sample feasibility studies to guide you – to speedup your work.

To place an order, email me to this address your specific needs.  If you have a PayPal account, then click the DONATE button in order to transfer payment to my PayPal account using the link below at the right hand side of the screen of my website:

http://energytechnologyexpert.com/

then click the DONATE button.

Once I have received email confirmation from PayPal that a payment has been completed and I received your order from my email address:

mars_ocampo@yahoo.com

or

energydataexpert@gmail.com

I will then send via email your desired project finance model.

In the absence of PayPal account or if  PayPal is not present in your country, you may apply for telegraphic transfer from a US Major Bank such as Citi Bank or Chase Manhattan Bank in your country to remit the payment to my local bank in the Philippines.  I will provide you my bank details once you have a firm order via email, similar to what I did for my clients from Africa (SI units) and America (English & NYMEX units).
Please refer to download file for sample data inputs and instructions for using the project finance model.

Regards,

Marcial T. Ocampo

Energy Technology & Pricing Expert

Project Finance & Financial Modeling

Energy & Business Development Consultant

—————- sample input data and instruction for running the project finance model

Instructions for Running this Project Finance Model (by Marcial T. Ocampo)

Enter the required data starting from the first step to the last step, then converge the model by pressing ctrl + d

0)

0

Include Carbon Emission Credits (CDM)

Blue cells are input fields for updating

These cells are case switches

1)

2

Define the NPV and return IRR to be used (1-4).

0

NPV-ROI return on investment (100% equity, 0% debt) – project cost versus cash flow (need to set equity to 0%)

1

NPV-ROE return on equity (say 30% equity, 70% debt) – equity portion of project cost versus cash flow (default)

0

NPV-FC return on equity (say 30% equity, 70% debt) – equity portion of project cost versus dividends flow (no depreciation)

0

NPV-FC discounted return on equity (say 30% equity, 70% debt) – equity portion of project cost versus discounted dividends flow (depreciating currency)

2)

25

Define the operating period (25 to 30 years) for the CCGT. This model is for 25 years but user may insert additional columns or delete columns to match period with project life.

2009

Define the end of construction period (year 0). It assumes everything has been constructed and finished at the end of this year (0) and will operate on following year (1).

3)

If you need to insert columns (increase operating period from 25 to say 30 years), place cursor at cell AA1

in both Main and Reports worksheet, then highlight to the right the number of columns to add, then insert columns.

Then copy the entire column range (AA10 .. AA615) in Main worksheet (the model sheet) up to the 2nd to the last column (say year 29)

Then copy the entire column range (AA1 .. AA277) in Reports worksheet (the report sheet) up to the 2nd to the last column (say year 29)

Be careful in copying the columns.  You must preserve the overhaul cycle for the overhaul and regular maintenance activities (rows 34 to 35) of Main worksheet.

4)

Define overhaul cycle and capacity degradation

1.00%

Normal, % p.a. normal degradation rate

-4.00%

Overhaul, % p.a. degradation recovered after overhaul

5

Overhaul Cycle, yr overhaul cycle

80.00%

Recovery, % fraction of normal degradation recovered during overhaul

6

per unit

5)

5

Select engine model & manufacturer (1-6)

MW gross

own use(1)

MW net

Heat Rate, kJ / kWh

Efficiency, %

Cost, $/kW

Variable O&M

Fixed O&M

MW gross

1

0

SGT6-5000F (Siemens Westinghouse)

264.061

1.457

262.604

6,611

54.45%

831.46

0.00200

0.150

264.061

1

0

GE PG 7121 EA x 2 (General Electric)

238.615

1.316

237.299

7,162

50.27%

975.61

0.00200

0.150

238.615

1

0

GE PG 7241 FA (General Electric)

236.292

1.303

234.989

6,576

54.74%

823.53

0.00200

0.150

236.292

1

0

SGT6-4000F (Siemens Westinghouse)

238.839

1.318

237.521

6,473

55.62%

832.02

0.00200

0.150

238.839

1

1

MHI501F3 (Mitsubishi Heavy Industries)

252.976

1.396

251.580

6,560

54.88%

801.59

0.00200

0.150

252.976

1

0

GT11N2 (Alstom)

321.048

1.771

319.277

7,115

50.60%

907.75

0.00200

0.150

321.048

Used

MHI501F3 (Mitsubishi Heavy Industries)

252.976

1.396

251.580

6,560

54.88%

801.59

0.00200

0.150

(1) Own use is mainly condenser cooling pumping power

6)

2

Select plant location / method of cooling of condenser (1-5)

Length, m

Head, m

Temp rise, deg C

Flow, m3/hr

kW Power(2)

% of Gross Power

Cost, $(3)

cooling medium flow rate

0

Once thru sea water

2,000.00

31.50

3.00

42,676

2,930.57

1.158%

7,439,378

sea water (m3/hr)

1

Once thru lake water

400.00

15.00

3.00

42,676

1,395.51

0.552%

7,397,716

lake water (m3/hr)

0

River water cooling tower

2,000.00

30.00

10.00

12,803

837.31

0.331%

7,332,480

river water (m3/hr)

0

Deep well water cooling tower

1,000.00

60.00

10.00

12,803

1,674.61

0.662%

14,664,961

deep well (m3/hr)

0

Radiator cooling

13.00

25,324

7,837.50

3.098%

8,792,214

ambient air (MT/hr)

Used

Once thru lake water

1,395.51

0.552%

7,397,716

(2) Power = 9.81 x (Q/3600) x H x 80% (3) Cost estimate of piping, pump, treatment, etc.

7)

Once thru cooling (sea water, lake water)

252.976

MWh / h

168.651

Heat to Boiler (2/3) since (1/3) goes to gas turbine

307

MWh / h

54.9%

Overall Fuel to Electricity Efficiency

fuel to electricity

307,319

kWh / h

1,000

kWh / MWh

1,106,348,373

kJ / h

3,600

kJ / kWh

1,048,611,807

BTU / h

1.05506

kJ / BTU

Energy input from fuel

891,320,036

BTU / h

85%

Boiler Efficiency

Energy to steam

157,291,771

BTU / h

15%

Heat Losses to Atmosphere

Energy to atmosphere & losses

891,320,036

BTU / h

Energy input to steam turbine

356,528,014

BTU / h

40%

Rankin Steam Turbine Efficiency

Energy to drive shaft

534,792,022

BTU / h

60%

Heat Losses to Condenser

Energy to condenser / cooling tower

356,528,014

BTU / h

Energy input to drive shaft

345,903,480

BTU / h

97%

Mechanical Drive (99%) & Generator Efficiency (98%) Energy to electricity

10,624,535

BTU / h

3%

Heat Losses to Generator

Energy to generator losses

534,792,022

BTU / h

Energy input to condenser / cooling tower

508,052,421

BTU / h

95%

Heat transferred to cooling water

Energy to cooling water

26,739,601

BTU / h

5%

Heat Losses to Atmosphere

Energy to atmosphere & losses

3.0

Allowable temperature Rise, deg C

Water allowable temperature rise

1.8

deg F per deg C rise

5.4

Allowable temperature Rise, deg F

1.00

Specific heat of lake water, Btu / lb deg F Water specific heat

94,083,782

lb / h

5.4

Allowable Btu / lb

42,676,123

kg / h

2.2046

lb / kg

42,676

cum / h

1,000

kg / cubic meter (kg / cum)

Cooling Water

8)

Water cooling tower (river water, deep well)

252.976

MWh / h

168.651

Heat to Boiler (2/3) since (1/3) goes to gas turbine

307

MWh / h

54.9%

Overall Fuel to Electricity Efficiency

fuel to electricity

307,319

kWh / h

1,000

kWh / MWh

1,106,348,373

kJ / h

3,600

kJ / kWh

1,048,611,807

BTU / h

1.05506

kJ / BTU

Energy input from fuel

891,320,036

BTU / h

85%

Boiler Efficiency

Energy to steam

157,291,771

BTU / h

15%

Heat Losses to Atmosphere

Energy to atmosphere & losses

891,320,036

BTU / h

Energy input to steam turbine

356,528,014

BTU / h

40%

Rankin Steam Turbine Efficiency

Energy to drive shaft

534,792,022

BTU / h

60%

Heat Losses to Condenser

Energy to condenser / cooling tower

356,528,014

BTU / h

Energy input to drive shaft

345,903,480

BTU / h

97%

Mechanical Drive (99%) & Generator Efficiency (98%) Energy to electricity

10,624,535

BTU / h

3%

Heat Losses to Generator

Energy to generator losses

534,792,022

BTU / h

Energy input to condenser / cooling tower

508,052,421

BTU / h

95%

Heat transferred to cooling water

Energy to cooling water

26,739,601

BTU / h

5%

Heat Losses to Atmosphere

Energy to atmosphere & losses

10.0

Allowable temperature Rise, deg C

Water allowable temperature rise

1.8

deg F per deg C rise

18

Allowable temperature Rise, deg F

1.00

Specific heat of lake water, Btu / lb deg F Water specific heat

28,225,134

lb / h

18

Allowable Btu / lb

12,802,837

kg / h

2.2046

lb / kg

12,803

cum / h

1,000

kg / cubic meter (kg / cum)

Cooling Water

9)

Radiator cooling (ambient air)

252.976

MWh / h

168.651

Heat to Boiler (2/3) since (1/3) goes to gas turbine

307

MWh / h

54.9%

Overall Fuel to Electricity Efficiency

fuel to electricity

307,319

kWh / h

1,000

kWh / MWh

1,106,348,373

kJ / h

3,600

kJ / kWh

1,048,611,807

BTU / h

1.05506

kJ / BTU

Energy input from fuel

891,320,036

BTU / h

85%

Boiler Efficiency

Energy to steam

157,291,771

BTU / h

15%

Heat Losses to Atmosphere

Energy to atmosphere & losses

891,320,036

BTU / h

Energy input to steam turbine

356,528,014

BTU / h

40%

Rankin Steam Turbine Efficiency

Energy to drive shaft

534,792,022

BTU / h

60%

Heat Losses to Condenser

Energy to condenser / cooling tower

356,528,014

BTU / h

Energy input to drive shaft

345,903,480

BTU / h

97%

Mechanical Drive (99%) & Generator Efficiency (98%) Energy to electricity

10,624,535

BTU / h

3%

Heat Losses to Generator

Energy to generator losses

534,792,022

BTU / h

Energy input to condenser / cooling tower

508,052,421

BTU / h

95%

Heat transferred to cooling air

Energy to cooling water

26,739,601

BTU / h

5%

Heat Losses to Atmosphere

Energy to atmosphere & losses

13.0

Allowable temperature Rise, deg C (10 TO 16) Allowable ambient air temperature rise

1.8

deg F per deg C rise

23.4

Allowable temperature Rise, deg F

0.389

Specific heat of air, Btu / lb deg F = 7/18 Ambient Air specific heat

55,829,936

lb / h

9.1

Allowable Btu / lb

25,324,293

kg / h

2.2046

lb / kg

25,324

MT / h

1,000

kg / MT

Cooling Ambient Air

10)

Define overhaul, maintenance, shutdown and outages

35

Planned Overhaul, days (5 wks)

21

Regular Maintenance, days (3 wks)

0.10%

Economic S/D, % of CD

0.50%

Deactivated S/D – External, % of CD

5.00%

Forced Outage – Internal, % of CD

95.00%

Load Factor, % of DC

11)

Define overhaul cycle and heat rate degradation

1.00%

Normal, % p.a. normal degradation rate

-4.00%

Overhaul, % p.a. degradation recovered after overhaul

5

Overhaul Cycle, yr overhaul cycle

80.00%

Recovery, % fraction of normal degradation recovered during overhaul

12)

Define transmission line (T/L) system and cost

Sea water

Lake water

River Water

Deep Well

Radiator

Selected

Line Voltage

kV

230

230

230

230

230

230

Power

kW

251,580

251,580

251,580

251,580

251,580

251,580

Length

km

20.00

10.00

15.00

15.00

25.00

10.00

1.609

km / mile

Power Factor

lag

0.85

0.85

0.85

0.85

0.85

0.85

Cost per kilometer of T/L

$/km

$360,000

$396,000

$432,000

$432,000

$324,000

$396,000

4

Conductor type (1-4)

Seaside City

Lakeside City

Riverside City

Riverside City

Inland City

ACSR (MCM)

% T/L Loss

% T/L Loss

% T/L Loss

% T/L Loss

% T/L Loss

Selected

1

ACSR (MCM) 336

2.477%

1.238%

1.858%

1.858%

3.096%

1.238%

2

ACSR (MCM) 795

1.185%

0.593%

0.889%

0.889%

1.482%

0.593%

AAC (MCM)

0.000%

3

AAC (MCM) 336

2.419%

1.210%

1.814%

1.814%

3.024%

1.210%

4

AAC (MCM) 789

1.030%

0.515%

0.773%

0.773%

1.288%

0.515%

Used

AAC (MCM) 789

1.030%

0.515%

0.773%

0.773%

1.288%

0.515%

13)

Define other power losses

1.00%

Step-up Transformer Loss (Switchyard), MWh

0.00%

Other Losses (non-technical, pilferage), MWh

14)

Define fuel properties

GHV, Btu/lb

NHV, Btu/lb

GHV / NHV

kg / Liter

Btu/liter

Reference

$/MMBtu

PhP / liter 2009

95.00%

Natural Gas (Malampaya Gas) – main fuel

22,129

20,249

1.093

2009

$GJ

8.628

9.10

418.11

PhP/GJ

5.00%

Diesel Oil – backup fuel (gas pipeline downtime)

19,650

18,453

1.065

0.8448

36,597

46.44

16.92

30.00

PhP/liter

4.00%

Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel

18,400

17,449

1.055

0.9659

39,181

35.97

12.24

23.24

PhP/liter

1.00%

Bunker Fuel Oil (BFO – 3% S) – boiler fuel

19,670

18,565

1.060

0.8916

38,664

34.84

12.01

22.51

PhP/liter

Lube Oil

0.8500

232.00

149.87

PhP/liter

2.2046

lb/kg

1.05506

kJ/Btu

15)

Lube Oil Consumption

1.00%

Normal, % p.a. normal degradation rate

-4.00%

Overhaul, % p.a. degradation recovered after overhaul

5

Overhaul Cycle, yr overhaul cycle

80.00%

Recovery, % fraction of normal degradation recovered during overhaul

0.254

Ideal Lube Oil Consumption, g/kWh

16)

0

Escalate fuel, lubes, tariff and O&M costs? (1=yes, 0=no)

Used

3.00%

Natural Gas (Malampaya Gas) – main fuel

0.00%

3.50%

Diesel Oil – backup fuel (gas pipeline downtime)

0.00%

2.50%

Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel

0.00%

2.00%

Bunker Fuel Oil (BFO – 3% S) – boiler fuel

0.00%

5.00%

Lube Oil

0.00%

17)

Escalation rates for tariff and O&M costs

Used

(e.g. US)

5.00%

Annual increase of the tariff, % p.a.

0.00%

Foreign (US)

US CPI

Local (RP)

RP CPI

% of operating income Calculated Paul Breeze

3.25%

Purchase of chemical materials

0.00%

70.00%

2.50%

30.00%

5.00%

0.40%

variable O&M

3.25%

Utilities (electricity, water)

0.00%

70.00%

2.50%

30.00%

5.00%

0.25%

variable O&M

0.00205

0.00200

4.25%

Maintenance of the installation

0.00%

30.00%

2.50%

70.00%

5.00%

5.000%

fixed O&M

4.25%

Personnel expense

0.00%

30.00%

2.50%

70.00%

5.00%

4.000%

fixed O&M

4.25%

Land lease, rent

0.00%

30.00%

2.50%

70.00%

5.00%

3.800%

fixed O&M

4.25%

Other services

0.00%

30.00%

2.50%

70.00%

5.00%

3.000%

fixed O&M

0.1514

0.1500

5.00%

Taxes, Insurances, Benefits & Regulatory Costs

0.00%

18)

Define electricity sales & revenues

Factor

Adjustment

70.00%

Electricity sales to DU, MWh

1.000

0.00%

discount price to direct customers (e.g. -10%)

20.00%

Electricity sales to NPC, MWh

1.000

0.00%

reference price to national grid (e.g. 0%)

10.00%

Electricity sales to WESM, MWh

1.000

0.00%

wholesale spot market price (e.g. +15%)

100.00%

Total must add to 100%

19)

Define working capital for initial project cost (months)

$/year

Working Capital

2

Total Fuel Costs

5,649,906

941,651

2

Expenses from lube purchase

82,955

13,826

2

Purchase of chemical materials

48,526

8,088

2

Utilities (electricity, water)

30,329

5,055

2

DOE 1-04 (0.01 PhP/kWh sold)

18,098

3,016

0.01

DOE 1-94 impost per kWh sold

2

Maintenance of the installation

606,576

101,096

48.46

PhP/US$ exchange rate

2

Personnel expense

485,260

80,877

2

Land lease, rent

460,997

76,833

2

Other services

363,945

60,658

Total working capital

7,746,593

1,291,099

20)

Define corporate income tax rate and income tax holiday

30%

Corporate income tax rate (% of taxable income)

0

Income tax holiday (ITH), years

21)

Expenses not eligible for income tax deduction

sample data

0.00%

Profit Sharing of income after tax

5.00%

0

Social Benefit Fund – Host Community per month

10,000

22)

Calculation of Working Capital Needs (WCN)

3.00

Cash needed for operations (+) months of expenses

1.00

Customers / Receivables (+) months of revenue

2.00

Stocks / Inventory (+) months of fuel & chemicals

1.00

Suppliers / Payables (-) months of payables

23)

Estimate all-in capital cost

000 PhP

check variance

Initial investment in land (US$/ha), 1 ha = 10,000 m2

1,000,000.00

10

ha

10,000

-

Freight on Board = FOB USA = $/kW

38,845.05

252.976

MW

9,826,866

-

Ocean Freight = FRT = 5% x FOB

5%

491,343

-

Insurance = INS = 1% x FOB

1%

98,269

-

Cargo, Insurance & Freight = CIF = FOB + FRT + INS

10,416,478

-

Value Added Tax = VAT = 12% x CIF

12%

1,249,977

-

Customs Duty = (CIF + VAT) x (% Duty) x (1 + % VAT)

3%

391,993

-

Duty-Paid Landed Cost = DPLC = CIF + VAT + Duty

12,058,448

-

Local Freight Cost = LFC = 3% x CIF

3%

312,494

-

Delivered Cost at Site = DCS = DPLC + LFC

12,370,942

-

Installation Cost = IC = 5% x FOB

5%

491,343

-

Condenser Cooling System

358,493,317

358,493

-

Transmission Line, $ per km and km length

19,190,160

10.00

km

191,902

-

Total EPC = DCS + IC+ CCS + T/L

13,412,680

-

Contingency (10%) = EPC x 10%

10%

1,341,268

-

Documentary Stamps (1%) = EPC x 1% = DS

1%

134,127

-

Total Fixed Assets (EPC + Contingency + DS)

14,888,075

-

Depreciation term (years)

salvage

10.00%

535,971

25

14,898,075

-

Development costs (modeler)

1.00%

148,981

-

Other Costs including taxes, contingencies

12.00%

1,787,769

-

Carbon Emission Registration & Consultancy

-

-

Initial investment in capitalized expenses

3,761,849

1,936,750

-

Amortization term (years)

salvage

10.00%

135,427

25

-

Working Capital:

-

Working capital (adjustments for DSCR = 1.1)

1.095

534,000

-

Working capital (initial stocks – fuel) – 2 months

941,651

-

Working capital (initial stocks – lubes) – 2 months

13,826

-

Working capital (initial stocks – chemical materials) – 2 months

8,088

-

Working capital (mobilization – utilities) – 2 months

5,055

-

Working capital (mobilization – DOE 1-94) – 2 months

3,016

-

Working capital (mobilization – maintenance) – 2 months

101,096

-

Working capital (mobilization – personnel expense) – 2 months

80,877

-

Working capital (pre-paid expense – advance rent) – 2 months

76,833

-

Working capital (pre-paid expense – other services) – 2 months

1,825,099

60,658

18,659,924

-

Interest During Construction:

-

Dev’t fees (loan arranger)

1.00%

186,599

-

Year -2

Year -1

Year 0

Front end fees (loan arranger)

1.00%

186,599

-

33.0%

33.0%

34.0%

Commitment fees (bank)

0.50%

94,233

-

6,157,775

6,157,775

6,344,374

Interest During Construction (bank) – 36 months

3.00

12.00%

4,455,990

4,923,421

-

6,157,775

12,315,550

18,659,924

Amortization term (years)

salvage

10.00%

177,243

25

-

62,511

31,722

0

Capital

Total Investment (land, fixed, capitalized expenses, working capital)

23,583,345

23,583,345

-

738,933

1,477,866

2,239,191

24)

Taxes, Insurances, Benefits & Regulatory Costs

Real Property Tax – Land

1.60%

of land

NOTE: Differentiate between one time, cyclic (every 2 or 5 years) and recurring (annual)

Real Property Tax – PPE

1.60%

of fixed assets

and vary the formula in the Main worksheet accordingly.

Real Property Tax – Buildings

0.80%

of building

For simplicity in this model, they are assumed to be annual fees to be conservative.

Land Lease & ROW

0.00

US$/MT coal

Property Insurance – PPE

0.78%

of fixed assets

Property Insurance – Building

0.78%

of building

Business Interruption Insurance

0.56%

of previous year’s revenue

of Capital

Special Education Fund – benefits to host community

1.00%

of land

0.277%

SEC Registration & Fees

65,325.87

Securities & Exchange Commission (certificate of registration)

BIR Registration & Fees

530.00

Bureau of Internal Revenue (registration of TIN, VAT)

0.007%

DENR Permits & Fees

1,650.83

Department of Environment & Natural Resources (EIS, ECC)

Discharge Fee (BOD, TSS) – DENR

0.00

water pollution discharge permit (4 wastes at 600 each)

0.028%

EMB Permits & Fees

6,603.34

Environment Management Bureau (air quality)

NWRB Permits & Fees

17,416.50

National Water Resources Board (water use permit)

PNRI Permits & Fees

5,900.00

Philippine Nuclear Research Institute (radioactive material license)

ERC Registration & Fess

1,500.00

Energy Regulatory Commission (certificate of compliance, authority to operate)

0.015%

DOLE Permits & Fees

3,537.50

Department of Labor & Employment (permit to operate pressurized vessels)

DTI Permits & Fees

0.00

Department of Trade & Industry (registration of business name, with SEC now for corporation)

0.142%

LGU Registration & Fees

33,488.35

Local government units (barangay, municipal, provincial, regional)

0.002%

NTC Registration & Fees

471.67

National Telecommunication Commission (radio station permit)

BOC Registration & Fees

5,000.00

Bureau of Customs (accreditation and registration)

PPA Registration & Fees

1,000.00

Philippine Port Authority (permit to operate shore line facilities)

ATO Registration & Fees

13,050.00

Air Transportation Office (height clearance permit for smoke stack)

PDEA Registration & Fees

3,000.00

Philippine Drug Enforcement Agency (essential chemicals commodity permit)

BOI Registration & Fees

4,500.00

Board of Investment (certificate of registration)

DOE Permits & Fees

800.00

Department of Energy (authority to import, certificate of registration)

Local Business Taxes (1/2 of 1% of GR)

0.00%

of gross revenue

National Franchise Taxes (1/2 of 1% of GR)

0.00%

of gross revenue

Total Taxes, Insurances, Benefits & Regulatory Costs

25)

Cost of debt (loan interest)

10.00%

Reference interest rate (Libor or other)

12

loan term

2.00%

Spread

3.00

grace period (construction period)

12.00%

Interest rate of debt

1

loan amortization method (1 = constant principal repayment, 0 = declining balance method)

26)

Capital Structure (equity & debt)

15.00%

% to be financed by capital

30.00%

Equity IRR

0.00%

% to be financed by non refundable subsidy

0.00%

Subsidy

12.00%

% to be financed by debt

70.00%

Debt Interest

Initial amount of capital

12.90%

WACC

27)

Debt Service Reserve Fund

6

months of debt service

4.00%

DSRF Income -interest on Foreign Currency Deposit

7.50%

Withholding Tax on Foreign Currency Deposit

0.30%

DSRF Expense – withholding tax

28)

Equity Structure (shareholder contribution)

planned

Annual dividend payable

actual

60.00%

Investor 1

83.57%

20.00%

Investor 2

-5.91%

20.00%

Investor 3

22.33%

29)

Your done.  Now converge the model by pressing ctrl + d

30)

Press ctrl + g to optimize CCGT engine and plant location

31)

Press ctrl + r to update Summary Table

32)

Press ctrl + q to update Sensitivity Table

33)

Vary electricity tariff and see impact on NPV, IRR and payback.

Go to Main worksheet

(impact of electricity tariff)

Update cell E5 (electricity tariff, $/kWh)

View results for NPV, IRR and payback (cells F6..H9)

Press ctrl + r to preserve Summary Table

34)

Determine capital cost given electricity tariff, fuel cost and O&M cost to meet IRR.

Go to Main worksheet

(impact of capital cost) – maximum capital cost to meet minimum IRR

Update cell E5 (electricity tariff, $/kWh)

Go to Sensitivity worksheet

Use goal seek to determine capital cost to meet IRR:

Set cell C16 (NPV) to zero by varying cell B9 (sensitivity factor for capital cost)

Press ctrl + r to preserve Summary Table

35)

Determine main fuel cost (pipeline natgas) given electricity tariff, capital cost and O&M cost to meet IRR. Go to Main worksheet

(impact of main fuel cost) – maximum fuel cost to meet minimum IRR

Update cell E5 (electricity tariff, $/kWh)

Go to Sensitivity worksheet

Use goal seek to determine capital cost to meet IRR:

Set cell C16 (NPV) to zero by varying cell B8 (sensitivity factor for main fuel cost)

Press ctrl + r to preserve Summary Table

36)

Determine rated capacity given electricity tariff, capital cost and O&M cost to meet IRR.

Go to Main worksheet

(impact of rated capacity) – minimum rated capacity to meet minimum IRR

Update cell E5 (electricity tariff, $/kWh)

Go to Sensitivity worksheet

Use goal seek to determine capital cost to meet IRR:

Set cell C16 (NPV) to zero by varying cell B10 (sensitivity factor for rated capacity)

Press ctrl + r to preserve Summary Table

(C) Copyright 2009 by Marcial T. Ocampo (November 2009)


2 Responses to “Project Finance Models for Power Plants with Carbon Credits under CDM (download file)”

  1. Micki Nitz Says:

    Dear, I always like this kind of articles, hope you can writer more the articles like this. I’m looking forward you!



  2. admin Says:

    Hi Micki (Miss or Mr),

    Thanks for your appreciative comment.

    Sure, I will continue writing articles of great importance and interest to my blog readers.

    Regards,

    Marcial



Leave a Reply

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>