Subscribe

Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC)

May 1st, 2010 Posted in Uncategorized

Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC)

A project finance model for calculating feed-in tariff to be paid to renewable energy developers to recover their cost of capital, generation cost and provide for reasonable profit using the DCF IRR method has been prepared for the National Renewable Energy Board (NREB) of the Philippines.

Thus, given the renewable energy (RE) capacity expansion plan (capacity, generation), an estimate on the annual budget to be paid to RE developers could be prepared.

The FiT model calculates the first year tariff and the levelized selling price (tariff), levelized cost of energy and generation (LCOE), and levelized profit, which is similar to the proforma income statement presentation.

The user simply updates an input sheet to enter the case input data and converges the model by pressing a macro that will vary the first year tariff so that the interplay of revenue (FiT) less generation costs (fixed O&M, variable O&M, fuels and lubes, regulatory costs, depreciation, interest on loan) will result in an equity discounted cash flow internal rate of return (equity DCF IRR) equal to the minimum investor returns.

Interested consultants, regulators, project developers may request for demo (protected) excel copies for their appreciation of the inputs, calculation procedures, reports, graphics and summaries, and once they are convinced that it is useful, they may place an order at the ENERGY DATA page of this blog, and remit payment via PayPal for the desired model.

Alternatively, you may place an order via email and I will provide you with my bank details to remit the payment via wire transfer.  Once confirmed that my PayPal or local bank account has received payment, I will then email two (2) excel (in xls format) file copies for your file.

Regards,

Marcial Ocampo

Energy Technology Selection and Business Development Consultant

mars_ocampo@yahoo.com

energydataexpert@gmail.com

——— SAMPLE REPORT SHEET

Executive Summary National Renewable Energy Board
BIOMASS PLANT Feed-in Tariff (FiT) Calculation Procedure
Investors’ Returns: NPV-FC Generation and Sales:
Equity IRR (% p.a.) 16.00% Capacity Factor (% of rated) 85.62%
Payback Period (years) 6.10 Days per year 365
Hours per day 24
Uses and Sources of Funds During Construction: 000 US$ $ / kW Gross Generation (MWh/year) 101,254
Power Plant Own Use (%) 10.000%
Uses of Funds: 10,125
Net Generation (MWh/year) 91,129
Initial investment in land (10 PhP/sqm) x (10,000 sqm/ha) 57.45 $4 Transmission Line Loss assumed (%) 3.000%
2,734
Freight on Board = FOB USA = $/kW 16,447.26 $1,218 Net Sales (MWh/year) 88,395
Ocean Freight = FRT = 5% x FOB 822.36
Insurance = INS = 1% x FOB 164.47 Transmission Line:
Cargo, Insurance & Freight = CIF = FOB + FRT + INS 17,434.09 Line Voltage 69 kV
Value Added Tax = VAT = 12% x CIF 2,092.09 Power 13,500 kW
Customs Duty = (CIF + VAT) x (% Duty) x (1 + % VAT) 0.00 Length 10.000 km
Duty-Paid Landed Cost = DPLC = CIF + VAT + Duty 19,526.18 Power Factor 0.850 lag
Local Freight Cost = LFC = 3% x CIF 523.02 No. of Circuit 3
Delivered Cost at Site = DCS = DPLC + LFC 20,049.21 Transmission Line Loss calculated (%) 0.307%
Installation Cost = IC = 5% x FOB 822.36 Cost per km: 2,000,000 PhP
Transmission line cost 69 kV (2,000,000 PhP/km) = T/L 425.53 42,553 $
Total EPC = DCS + IC + T/L 21,297.10 Capital and O&M Cost Assumptions:
Contingency (10%) = EPC x 10% 2,129.71 Cost per kW FOB USA ($/kW) 1,218
Documentary Stamps (1%) = EPC x 1% = DS 212.97 Variable O&M ($/kWh): 0.00520 Year 1
Total Fixed Assets (EPC + Contingency + DS) 23,639.78 $1,751 Purchase of chemical materials (100%) 203.58 000 US$
Utilities (fuel, lubes, electricity, water) (150%) 305.37 000 US$
Capitalized Expenses: Fixed O&M ($/kW/year) 0.430
Development costs (developer, modeler) 118.49 Maintenance of the installation (100%) 1,814.06 000 US$
Other Costs including taxes, contingencies 0.00 Personnel expense (100%) 1,814.06 000 US$
Carbon Emission Registration & Consultancy 35.00 Land lease, rent (60%) 1,088.44 000 US$
Initial investment in capitalized expenses 153.49 $11 Taxes, Insurance, services, and others (40%) 725.63 000 US$
Transport (20%) 362.81 000 US$
Working Capital: DSRF Expense 4.71 000 US$
months Regulatory Costs:
Working capital (adjustment to meet DSCR = 1.1) 0.00 Special Privilege Tax – 2% 195.60 000 US$
Expenses from biomass purchase 1,208.10 2 Special Realty Tax – 2.5% 430.51 000 US$
Purchase of chemical materials (100%) 33.93 2 DOE 1-94 : 0.01 PhP/kWh sales 18.81 000 US$
Utilities (fuel, lubes, electricity, water) (150%) 76.34 3 Debt Service Reserve Fund:
Maintenance of the installation (100%) 453.52 3 Months of debt service 6
Personnel expense (100%) 453.52 3 DSRF Income -interest on Foreign Currency Deposit 4.0%
Land lease, rent (60%) 90.70 1 Withholding Tax on Foreign Currency Deposit 7.5%
Taxes, Insurance, services, and others (40%) 60.47 1 DSRF Expense 0.30%
Transport (20%) 30.23 1 Taxes and Regulatory Costs:
Total Working Capital 2,406.81 $178 Special Privilege Tax – 2% 1.00%
Special Realty Tax – 2.5% 1.50%
Interest During Construction: DOE 1-94 : 0.01 PhP/kWh sales 0.01
Dev’t fees (developer, loan arranger) 131.29 Corporate income tax rate (% of taxable income) 10%
Front end fees (modeler, loan arranger) 131.29 Income tax holiday (ITH), years 7
Commitment fees (bank) 131.29 Profit Sharing, % of IAT 0.00%
Interest During Construction (bank) – 18 months 3,938.63 Social Benefit Fund – Host Community, PhP/month 0
Total Legal & Financing Fees and IDC 4,332.49 $321 Working Capital Needs: months
Cash needed for operations (+) 3.00
Total Uses of Fund, ’000 US$ 30,590.01 $2,266 Customers / Receivables (+) 1.00
Stocks / Inventory (+) 2.00
Suppliers / Payables (-) 1.00
Sources of Fund:
Exchange Rate and Escalation: 0 No Escalation
% to be financed by capital 9,177.00 30.00% Exchage Rate, PhP / US$ 47.00 0.00% depreciation
% to be financed by non refundable subsidy 0.00 0.00% RP CPI (Local) 5.00% local escalation
% to be financed by debt 21,413.01 70.00% US CPI (Foreign) 2.50% foreign escalation
Total Sources of Fund, ’000 US$ 30,590.01 100.00% First Year Tariff (PhP/kWh) 10.4000 0.00% tariff escalation
Variable O&M: weight 0.00% variable escalation
Weighted Average Cost of Capital (WACC): Returns % Local (30%) 50.00% 5.00%
Equity 16.00% 30.00% % Foreign (70%) 50.00% 2.50%
Subsidy 0.00% 0.00% Fixed O&M: weight 0.00% fixed escalation
Debt 10.00% 70.00% % Local (70%) 50.00% 5.00%
WACC 11.80% % Foreign (30%) 50.00% 2.50%
Loan: Fuel & Lubes Properties: Btu/lb kg/L % fuel blend
Interest rate of debt, % p.a. 10.00% Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel 18,400 0.9659 0.00%
Loan term, years 12 Biomass (Solid Waste, Woodwaste, Landfill Gas, Biogas) 4,000 100.00%
Grace period (construction period), months 18.00 Lube Oil 0.8500 100.00%
Fuel & Lubes Costs & Escalation: PhP/L
Rated Capacity: Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel 27.11 0.00% diesel escalation
Unit Capacity (MW/unit) 13.500 Biomass (Solid Waste, Woodwaste, Landfill Gas, Biogas) 2.00 0.00% bunker escalation
No. of Units 1 Lube Oil 174.85 0.00% lube escalation
Total Gross Installed Capacity (MW) 13.500 Plant Heat Rate and Lube Oil Rate:
Plant Own Use (MW) 1.350 10.00% Diesel Engine Heat Rate (Btu/kWh gross) 14,835 23.00% thermal efficiency
Net Capacity (MW) 12.150 Lube Oil Consumption Rate (g/kWh) 0.2535 not used
Name BIOMASS PLANT National Renewable Energy Board
(C) Copyright 2009 by Marcial T. Ocampo (November 2009) Feed-in Tariff (FiT) Calculation Procedure
WITH INCENTIVES UNDER RE LAW
TO ORDER: http://energytechnologyexpert.com/energy-technology-finance-models/

——— SAMPLE INPUT SHEET

Instructions for Running this Project Finance Model (by Marcial T. Ocampo) – US Dollar Model Licensed for: National Renewable Energy Board
Enter the required data starting from the first step to the last step, then converge the model by pressing ctrl + e press ctrl + e to converge model (DCF IRR)
0) 1 Select DCF IRR (1) or RORB (0) Blue cells are input fields for updating
1 Include Carbon Emission Credits (1), no CER (0) 10 years These cells are case switches
0 Include Depreciation (1), no depreciation (0)
1) 3 Define the NPV and return IRR to be used (1-3).
0 NPV-ROI return on investment (100% equity, 0% debt) – project cost versus cash flow
0 NPV-ROE return on equity (say 30% equity, 70% debt) – equity portion of project cost versus cash flow
1 NPV-FC return on equity (say 30% equity, 70% debt) – equity portion of project cost versus dividends flow (free cash) – default
47.00 Exchage Rate, PhP / US$
2) 5.00% RP CPI (Local) Philippine escalation rate, % p.a.
2.50% US CPI (Foreign) US escalation rate, % p.a.
3) 2010 Define the end of construction period (year 0). It assumes everything has been constructed and finished at the end of this year (0) and will operate on following year (1).
4) Rated Capacity and Losses Unit Capacity No. of Units
13.500 Rated Capacity (RC), MW 13.500 1 88695 MWh 13.5 MW
10.00% Power Plant Own Use 0.75 6570
3.00% Transmission Line Losses (10 km line) Select red cells below for T/L losses
Transmission Line Losses
Line Voltage 69 kV km 1.609
Power 13,500 kW mile 1
Length 10.00 km feet 5280
Power Factor 0.85 lag
Total Line Current 132.894 A resistivity of Al 20 17.002 ohm-cmil/ft
Line Current/Circuit 44.298 A 25 17.345 ohm-cmil/ft
No. of Circuit 3
Transmission Line Cost of T/L Cost of T/L With 50%
Used Conductor Type Ampacity Resistance (ohms/mile) Loss (3-phase)* $ / km PhP / km allowance
ACSR (MCM) A 25 deg.C 50 deg.C 90 deg.C kW %
0 336 530 0.278 0.306 0.351 99.68 0.738% $25,532 1,200,000 1.11%
0 795 900 0.119 0.138 0.168 47.71 0.353% $29,787 1,400,000 0.53%
AAC (MCM) A 20 deg.C 25 deg.C 90 deg.C kW
0 336 495 0.267 0.273 0.343 97.36 0.721% $34,043 1,600,000 1.08%
1 789 855 0.114 0.116 0.146 41.46 0.307% $42,553 2,000,000 0.46%
USED 0.307% $42,553 2,000,000 0.46%
5) Capacity Factor (365 days, 5 year cycle) 1 2 3 4 5 Average
42 Planned Overhaul, days (6 wks) 42
14 Regular Maintenance, days (2 wks) 14 14 14 14
0.10% Economic S/D, % of CD 0.365 0.365 0.365 0.365 0.365
0.50% Deactivated S/D – External, % of CD 1.825 1.825 1.825 1.825 1.825
8.00% Forced Outage – Internal, % of CD 29.2 29.2 29.2 29.2 29.2
98.16% Load Factor, % of DC 45.39 45.39 45.39 45.39 73.39 50.99 vary load factor to hit 75%
85.62% Capacity Factor, % of RC 319.61 319.61 319.61 319.61 291.61 314.01
CD = Calendar Days (365 days per year) 88.78% 88.78% 88.78% 88.78% 81.00% 87.23%
RC = Rated Capacity, MW 98.16% 98.16% 98.16% 98.16% 98.16% 98.16%
DC = Dependable Capacity, MW (after degradation) 87.15% 87.15% 87.15% 87.15% 79.51% 85.62%
6) Define overhaul cycle and capacity degradation
0.50% Normal, % p.a. normal degradation rate
-2.00% Overhaul, % p.a. degradation recovered after overhaul
5 Overhaul Cycle, yr overhaul cycle
80.00% Recovery, % fraction of normal degradation recovered during overhaul
7) Define overhaul cycle and heat rate degradation
0.50% Normal, % p.a. normal degradation rate
-2.00% Overhaul, % p.a. degradation recovered after overhaul
5 Overhaul Cycle, yr overhaul cycle
80.00% Recovery, % fraction of normal degradation recovered during overhaul
8) 3 Plant Heat Rate (enter type of engine, 1-3) 1=CCGT 2=Diesel 3=Thermal
GT Gas Turbine Output (1 / 3) 33.33% 40.00%
ST Steam Turbine Input (2 / 3) 66.67%
BE Boiler Efficiency at 1% cont. BD 85.00% 73.60% vary this entry to hit 23%
STE Steam Turbine Efficiency 40.00% 35.00%
ME Mechanical Drive / Clutch Efficiency 99.00% 97.00% 95.00%
GE Generator Efficiency 98.00% 96.00% 94.00%
OE 23.00% Overall Efficiency=(GT+ST*BE*STE)*ME*GE 54.33% 37.25% 23.00%
Plant Heat Rate at 100% eff. (3600 / 1.05506), Btu/kWh 3412.12822
PHR Plant Heat Rate, Btu / kWh = 3412/ OE 6,280 9,160 14,835
0 0 1
9) Define fuel properties GHV, Btu/lb NHV, Btu/lb GHV / NHV kg / Liter Btu/liter Reference $/MMBtu PhP / liter 2009
0.00% Natural Gas (Malampaya Gas) – main fuel 22,129 20,249 1.093 2009 $GJ 8.628 9.10 405.52 PhP/GJ
0.00% Diesel Oil – backup fuel (gas pipeline downtime) 19,650 18,453 1.065 0.8448 36,597 46.44 20.35 35.00 PhP/liter
0.00% Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel 18,400 17,449 1.055 0.9659 39,181 35.97 14.72 27.11 PhP/liter
0.00% Bunker Fuel Oil (BFO – 3% S) – boiler fuel 19,670 18,565 1.060 0.8916 38,664 34.84 14.45 26.26 PhP/liter
0.00% Coal (Lignite, Bituminous, Anthracite) – thermal 10,000 9,475 1.055 $85.00 3.86 4.00 PhP/kg
100.00% Biomass (Solid Waste, Woodwaste, Landfill Gas, Biogas) 4,000 3,463 1.155 7.38% 4.83 2.00 PhP/kg
Lube Oil 0.8500 232.00 174.85 PhP/liter
3600 kJ/kWh 2.2046 lb/kg 1.05506 kJ/Btu
1000 kg/MT
10) Lube Oil Consumption
0.50% Normal, % p.a. normal degradation rate
-2.00% Overhaul, % p.a. degradation recovered after overhaul
5 Overhaul Cycle, yr overhaul cycle
80.00% Recovery, % fraction of normal degradation recovered during overhaul
0.254 Ideal Lube Oil Consumption, g/kWh
11) 0 Escalate fuel, lubes, tariff and O&M costs? (1=yes, 0=no) Used
3.00% Natural Gas (Malampaya Gas) – main fuel 0.00%
3.50% Diesel Oil – backup fuel (gas pipeline downtime) 0.00%
2.50% Low Sulfur Fuel Oil (LSFO – 1% S) – boiler fuel 0.00% biomass price is tied-up to LSFO price
2.00% Bunker Fuel Oil (BFO – 3% S) – boiler fuel 0.00%
2.00% Coal (Lignite, Bituminous, Anthracite) – thermal 0.00%
2.50% Biomass (Solid Waste, Woodwaste, Landfill Gas, Biogas) 0.00%
5.00% Lube Oil 0.00%
12) % p.a. Escalation rates for tariff and O&M costs Used Foreign (US) US CPI Local (RP) RP CPI
3.75% Purchase of chemical materials (100%) 0.00% 50.00% 2.50% 50.00% 5.00% variable O&M
3.75% Utilities (fuel, lubes, electricity, water) (150%) 0.00% 50.00% 2.50% 50.00% 5.00% variable O&M
3.75% Maintenance of the installation (100%) 0.00% 50.00% 2.50% 50.00% 5.00% fixed O&M
3.75% Personnel expense (100%) 0.00% 50.00% 2.50% 50.00% 5.00% fixed O&M
3.75% Land lease, rent (60%) 0.00% 50.00% 2.50% 50.00% 5.00% fixed O&M
3.75% Taxes, Insurance, services, and others (40%) 0.00% 50.00% 2.50% 50.00% 5.00% fixed O&M
3.75% Transport (20%) 0.00% 50.00% 2.50% 50.00% 5.00% fixed O&M
13) Define electricity sales & revenues Factor Adjustment
70.00% Electricity sales to DU, MWh 1.000 0.00% discount price to direct customers (e.g. -10%)
20.00% Electricity sales to NPC, MWh 1.000 0.00% reference price to national grid (e.g. 0%)
10.00% Electricity sales to WESM, MWh 1.000 0.00% wholesale spot market price (e.g. +15%)
100.00% Total must add to 100%
000 US$ Byproduct Sales PhP/year Escalation
0 Initial amount of sales of by-products, ’000 US$ 0 0.00%
0 Other operating income from the plant, ’000 US$ 0 0.00%
for cogen only for biomass
14) months Define working capital for initial project cost (months) 000 $/year Working Capital PSMA Paul Breeze
2 Expenses from biomass purchase 7,249 1,208
2 Purchase of chemical materials (100%) 204 34 variable O&M 0.700 PhP/kWh 0.00520 $/kWh
3 Utilities (fuel, lubes, electricity, water) (150%) 305 76
3 Maintenance of the installation (100%) 1,814 454 fixed O&M 0.846 PhP/kWh 0.4300 $/kW/year
3 Personnel expense (100%) 1,814 454
1 Land lease, rent (60%) 1,088 91 land lease from NorthWind
1 Taxes, Insurance, services, and others (40%) 726 60 ha PhP PhP/yr $/yr
1 Transport (20%) 363 30 100 7,500 750,000 15,957
Total working capital 13,563 2,407
15) Total Regulatory Expenses
1.00% Special Privilege Tax – 2% of Electricity Revenue
1.50% Special Realty Tax – 2.5% of Depreciated Project Cost
0.01 DOE 1-94 : 0.01 PhP/kWh sales PhP/kWh sales
16) Define corporate income tax rate and income tax holiday
10% Corporate income tax rate (% of taxable income)
7 Income tax holiday (ITH), years
17) Expenses not eligible for income tax deduction sample data
0.00% Profit Sharing, % of IAT of income after tax 5.00% not used
0 Social Benefit Fund – Host Community, PhP/month per month 10,000 not used
18) Calculation of Working Capital Needs (WCN)
3.00 Cash needed for operations (+) months of expenses
1.00 Customers / Receivables (+) months of revenue
2.00 Stocks / Inventory (+) months of fuel & chemicals
1.00 Suppliers / Payables (-) months of payables
19) 47.00 Estimate all-in capital cost check variance PhP/sqm sqm/ha
$4 Initial investment in land (10 PhP/sqm) x (10,000 sqm/ha) $2,128 27 ha 57 - 10 10000
Freight on Board = FOB USA = $/kW $1,218 13.500 MW 16,447 -
Ocean Freight = FRT = 5% x FOB 5% 822 -
Insurance = INS = 1% x FOB 1% 164 -
Cargo, Insurance & Freight = CIF = FOB + FRT + INS 17,434 -
Value Added Tax = VAT = 12% x CIF 12% 2,092 -
Customs Duty = (CIF + VAT) x (% Duty) x (1 + % VAT) 0% 0 -
Duty-Paid Landed Cost = DPLC = CIF + VAT + Duty 19,526 -
Local Freight Cost = LFC = 3% x CIF 3% 523 -
Delivered Cost at Site = DCS = DPLC + LFC 20,049 -
Installation Cost = IC = 5% x FOB 5% 822 -
Transmission line cost 69 kV (2,000,000 PhP/km) = T/L $42,553 10.0 425.53 -
Total EPC = DCS + IC + T/L 21,297.10 -
Contingency (10%) = EPC x 10% 10% 2,130 -
Documentary Stamps (1%) = EPC x 1% = DS 1% 213 -
$1,751 Total Fixed Assets (EPC + Contingency + DS) 23,640 -
Depreciation term (years) salvage value 10.00% 1,418 15 23,697 -
Development costs (developer, modeler) 0.50% 118 -
Other Costs including taxes, contingencies 0.00% - -
Carbon Emission Registration & Consultancy 35 -
$11 Initial investment in capitalized expenses 2,560 153 -
Amortization term (years) salvage value 10.00% 154 15 -
Working Capital: -
0.513 Working capital (adjustments for DSCR = 1.1) 1.100 1.613 - -
Expenses from biomass purchase 2 1,208 -
Purchase of chemical materials (100%) 2 34 -
Utilities (fuel, lubes, electricity, water) (150%) 3 76 -
Maintenance of the installation (100%) 3 454 -
Personnel expense (100%) 3 454 -
Land lease, rent (60%) 1 91 -
Taxes, Insurance, services, and others (40%) 1 60 -
$178 Transport (20%) 1 2,407 30 26,258 -
Interest During Construction: -
Dev’t fees (developer, loan arranger) 0.50% 131 -
Front end fees (modeler, loan arranger) 0.50% 131 -
$321 Commitment fees (bank) 0.50% 131 -
Interest During Construction (bank) – 36 months 18 10.00% 3,939 4,332 -
Amortization term (years) salvage value 10.00% 260 15 -
$2,266 Total Investment (land, fixed, capitalized expenses, working capital) 30,628 30,590 -38 -
target cost variance
20) Taxes, Insurances, Benefits & Regulatory Costs based on 47.00 PhP/US$
Real Property Tax – Land 1.60% of land NOTE: Differentiate between one time, cyclic (every 2 or 5 years) and recurring (annual)
Real Property Tax – PPE 1.60% of fixed assets and vary the formula in the Main worksheet accordingly.
Real Property Tax – Buildings 0.80% of building For simplicity in this model, they are assumed to be annual fees to be conservative.
Land Lease & ROW 0.00 US$/MT coal
Property Insurance – PPE 0.78% of fixed assets
Property Insurance – Building 0.78% of building
Business Interruption Insurance 0.56% of previous year’s revenue
of Capital Special Education Fund – benefits to host community 1.00% of land
0.277% SEC Registration & Fees 84.73 Securities & Exchange Commission (certificate of registration)
BIR Registration & Fees 11.28 Bureau of Internal Revenue (registration of TIN, VAT)
0.007% DENR Permits & Fees 2.14 Department of Environment & Natural Resources (EIS, ECC)
Discharge Fee (BOD, TSS) – DENR 0.00 water pollution discharge permit (4 wastes at 600 each)
0.028% EMB Permits & Fees 8.57 Environment Management Bureau (air quality)
NWRB Permits & Fees 370.56 National Water Resources Board (water use permit)
PNRI Permits & Fees 125.53 Philippine Nuclear Research Institute (radioactive material license)
ERC Registration & Fess 31.91 Energy Regulatory Commission (certificate of compliance, authority to operate)
0.015% DOLE Permits & Fees 4.59 Department of Labor & Employment (permit to operate pressurized vessels)
DTI Permits & Fees 0.00 Department of Trade & Industry (registration of business name, with SEC now for corporation)
0.142% LGU Registration & Fees 43.44 Local government units (barangay, municipal, provincial, regional)
0.002% NTC Registration & Fees 0.61 National Telecommunication Commission (radio station permit)
BOC Registration & Fees 106.38 Bureau of Customs (accreditation and registration)
PPA Registration & Fees 21.28 Philippine Port Authority (permit to operate shore line facilities)
ATO Registration & Fees 277.66 Air Transportation Office (height clearance permit for smoke stack)
PDEA Registration & Fees 63.83 Philippine Drug Enforcement Agency (essential chemicals commodity permit)
BOI Registration & Fees 95.74 Board of Investment (certificate of registration)
DOE Permits & Fees 17.02 Department of Energy (authority to import, certificate of registration)
Local Business Taxes (1/2 of 1% of GR) 0.00% of gross revenue
National Franchise Taxes (1/2 of 1% of GR) 0.00% of gross revenue
Total Taxes, Insurances, Benefits & Regulatory Costs
21) Cost of debt (loan interest)
8.00% Reference interest rate (Libor or other), % p.a. 12 Loan term, years
2.00% Spread, % p.a. 18.00 Grace period (construction period), months
10.00% Interest rate of debt, % p.a. 0 Loan amortization method (1 = constant principal repayment, 0 = declining balance method)
22) Capital Structure (equity & debt)
16.00% % to be financed by capital 30.00% Equity IRR
0.00% % to be financed by non refundable subsidy 0.00% Subsidy
10.00% % to be financed by debt 70.00% Debt Interest
Initial amount of capital 11.80% WACC
23) Debt Service Reserve Fund
6 Months of debt service
4.00% DSRF Income -interest on Foreign Currency Deposit
7.50% Withholding Tax on Foreign Currency Deposit
0.30% DSRF Expense – withholding tax
24) Equity Structure (shareholder contribution)
planned Annual dividend payable actual
60.00% Investor 1
20.00% Investor 2
20.00% Investor 3
25) Your done. Now converge the model by pressing ctrl + e
26) Print the reports as required
Name BIOMASS PLANT National Renewable Energy Board
(C) Copyright 2009 by Marcial T. Ocampo (November 2009) Feed-in Tariff (FiT) Calculation Procedure
WITH INCENTIVES UNDER RE LAW
TO ORDER: http://energytechnologyexpert.com/energy-technology-finance-models/

———

12 Responses to “Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC)”

  1. Austin Car Insurance Says:

    Great Site! I wondered if I could quote a portion of your website and use a couple of points for a term paper. Please drop me an email if that would be fine. Thanks



  2. admin Says:

    Hi, sure, okay to quote a portion of my website. thanks. marcial



  3. Portland injury attorney Says:

    Found your website on AskJeeves, great written content, but the site looks awkward inside browser setup, but is effective fine in IE. travel figure.



  4. Beaulah Ensminger Says:

    Hiya, I am really glad I have found this information. Today bloggers publish only about gossip and net stuff and this is actually irritating. A good site with exciting content, that is what I need. Thank you for making this web site, and I will be visiting again. Do you do newsletters? I Can not find it.



  5. backlink builder Says:


  6. london gas safety certificate Says:

    gas safety certificate…

    [...]Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC) | Energy Technology Expert[...]…



  7. EPC Worcester Says:

    EPC Worcester…

    [...]Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC) | Energy Technology Expert[...]…



  8. gout pain Says:

    gout pain…

    [...]Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC) | Energy Technology Expert[...]…



  9. alternative source of energy Says:

    alternative source of energy…

    [...]Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC) | Energy Technology Expert[...]…



  10. Solar PV Installers UK Says:

    Solar PV Installers UK…

    [...]Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC) | Energy Technology Expert[...]…



  11. how can i get taller fast Says:

    how can i get taller fast…

    [...]Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC) | Energy Technology Expert[...]…



  12. to how draw cool Says:

    to how draw cool…

    [...]Feed-in Tariff Calculation Models for sale – biomass, cogen, mini-hydro, wind, solar and ocean thermal energy conversion (OTEC) | Energy Technology Expert[...]…



Leave a Reply

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>